Dates |
(State: 10.11.2008) |
OUTLOOK |
|
November 2008 | Test curtain grouting |
|
November - December 2008 | Finishing the final design for the final phase of the Bribin hydropower plant |
|
March - April 2009 | Shipping of KSB-modules to Indonesia |
|
May - April 2009 | Installation of KSB-modules |
|
June 2009 | Commissioning and operation of Bribin hydropower plant |
|
11.10 - 27.10.2008 | Installation the controlling system (electro techniques) from Walcher Ltd. |
|
06.10 - 11.10.2008 | 2nd test Storage and pump water to Kaligoro reservoir |
|
08.10 - 09.10.2008 | Kick-Off Meeting of BMBF-Joint Project Integrater Water- and Ressources Management (IWRM) in Gunung Kidul, Yogyakarta in Indonesia |
|
from Sept. 2008 | Production of the KSB-modules for the final phase |
|
01.08.2008 | Test-run of KSB-Module |
|
29.07. - 01.08.2008 | Successfull test storage (see also KIT Pressrelease) as well as monitoring of barrage movement and seepage water |
|
25.07.2008 | Completion of contact grouting at the Barrage |
|
06.07. - 14.07.2008 | Installation of VAG-valves at the flood relief lines |
|
05.05. - 09.05.2008 | Presentation of the Project at the IFAT-Convention in Munich |
|
13.03.2008 | Presentationon of the project at the 5th symposium "Baustoffe und Bauwerkshaltung" at the University of Karlsruhe (TH) |
|
23.01. - 31.01.2008 | Installation the first KSB turbine-pump module |
|
22.01.2008 | Completion the barrage |
|
26.12.2007 | Interuption of the construction works due to the flood event (Q > 9 m3/s) |
|
25.12.2007 | Completion the fifth step concreting work of the barrage (5 of 6) |
|
19.12.2007 | Completion the fourth step concreting work of the barrage (4 of 6) |
|
09.12. - 18.12.2007 | Installation of the wall pipes at the barrage |
|
05.12.2007 | Completion the third step concreting work of the barrage (3 of 6) |
|
02.12.2007 | Completion the second step concreting work of the barrage (2 of 6) |
|
27.11.2007 | Conpletion the first step concreting work of the barrage (1 of 6) |
|
20.11.2007 | Erection the Tower Crane |
|
October 2007 | IWRM survey campaign of Bribin water distribution networks and determine the location of drilling test for Gua Seropan, conducted by GIK |
|
August 2007 | Continuation of the construction works in Bribin |
|
25.07. - 26.07.07 | 4th Workshop of Integrated Water Resources Management in Yogyakarta: "Bribin Project after Earthquake 2006 & Opening Ceremony of IWRM", attended by deputy director Asia, International Office of BMBF, Frau Dr. Heike Bauer and Herr Dr. Andreas Suthhof |
|
07.06. - 11.06.07 | Assess the construction site / rock abutment / barrage foundation / rock bolts |
|
04.06. - 06.06.07 | Completion of the dewatering works at the construction site |
|
14.04. - 24.04.07 | Second blasting activities at the rockfall behind siphon by Indonesian explosive company with support of german professional divers |
|
05.03. - 09.03.07 | DAAD-Workshop at the Institute of Technology Bandung (ITB) under coordination of IWG in cooperation with CEDIM |
|
26.01. - 02.02.07 | Coordination for the continuation work of the projects (Bribin, Ad-hoc and IWRM) |
|
27.12. - 13.01.07 | Evaluation of Ad-hoc project and distribution of the donation (school books) from the industry partner Herrenknecht to the elementary schools in Gunung Kidul (Ad-hoc) |
|
09.11.2006 | 3rd Workshop of Integrated Water Resources Management. Subtopic: Prospect for development of Bribin and Seropan caves after earthquake. Organize by Goverment of Yogyakarta Special Province |
|
04.11. - 13.11.2006 | First blasting activities at the rockfall behind siphon by Indonesian explosive company with support of german professional divers |
|
07.11. - 08.11.2006 | Visit of the German Ambassador for Indonesia, Mr. Freiherr v. Mahltzahn, and BMBF delegation: Mr. RD Ollig, Mr. Lahr and Mrs. Heyn in the project area with project presentation, construction site inspection and cave expedition, as well as meeting with Sri Sultan HB X in Yogyakarta |
|
02.11. - 29.11.2006 | Development of sanitation system and toilet building at the Glompong elementary school (Ad-hoc) |
|
27.09. - 29.09.2006 | Presentation at Wasserbausymposium Graz 2006 (Water Resources Symposium) |
|
22.09. - 07.10.06 | Assignment of german divers for the preparation of blasting works at the rockfall in Gua Bribin; first blasting test at the quarry in Jember, East Java |
|
13.09. - 15.10.06 | IWRM - survey campaign in Gua Seropan and the project area by GIK, VA SHS and IWG |
|
24.08. - 07.09.06 | Development of drinking water filtration at the Glompong elementary school and installation of UV-Water Filtration at Wonosari hospital (Ad-hoc) |
|
Oct. - Dec. 06 | Building three information centre (POSYANIS) in the earthquake area under the frame of a student project "Student Support for Yogya Earthquake Reconstruction Processes" in cooperation with the Civil Engineering Department, University of Gadjah Mada, Yogyakarta (Ad-hoc) |
|
31.07. - 02.08.06 | Visit of Deputy Director Asia, International Office of BMBF, Frau Dr. Heike Bauer, in the project area with project presentation and construction site inspection |
|
08.07. - 05.08.06 | Assign a German cave diver to Gua Bribin and Seropan for detail investigations of possible damages that were caused by the Earthquake. Find the rockfall behind the last siphon which were released by the earthquake event. |
|
Jun.06 - Aug.06 | Reconstruction of school building in Glompong village by Committee Cap-Anamur in cooperation with University of Karlsruhe (Ad-hoc) |
|
Jun.06 | Initiate an Ad-hoc project as an additional (aid) project for the Earthquake at Yogyakarta Province, in cooperation with BMBF and Committee Cap-Anamur |
|
30.05.06 | First relief action in the catastrophe (earthquake) region by the committee Cap Anamur in cooperation with the university Karlsruhe |
|
27.05.06 | Severe earthquake at the province Yogyakarta, with death toll more than 6.000 people. The karst region Gunung Kidul is also highly affected; immediate the waterlevel rises approx. 1,5 m at the Gua Bribin construction site |
|
03.04. - 07.04.06 | Presentation of the project at the "Wasser Berlin 2006" with a exhibition model of the IWG |
|
Jan. 2006 | Delivery of pump and turbine modules to Indonesia for the implementation of the first phase |
|
Dec. 2005 | Completion of platform construction
in Gua Bribin Interuption of the construction works due to the severe flood event (Beginning of the rainy season) |
|
27.11. - 29.11.2005 | DAAD-Alumni-Seminar "Engineering for Environment" in Bandung / strategy discussion with the government authorities regarding the current Bribin Project and the planned IWRM project under the consideration of Sri Sultan HBX |
|
10.11.2005 | Press conference at the University of Karlsruhe |
|
Oct. 2005 | Delivery of KSB-pump modules as well as the control system from Walcher Ltd. |
|
14.10. - 23.10.2005 | Geological and geotechnical evaluation of the subsoil by an expert team from the University of Karlsruhe |
|
27.09. - 28.09.2005 | Final inspection of pump modules (I, II) as well as the control system in the test facilities of KSB |
|
Sep. 2005 | Completion of dewatering for further construction works in Bribin cave |
|
23.07. - 10.08.2005 | Assign a
German cave diver team to investigate the undercurrent of siphon in the
construction area. Exploration of unknown lateral courses in Gua Bribin for the discharge capacity analysis in the case of flood |
|
25.04. – 29.04.2005 | Presentation of the project at the IFAT-Convention in Munich |
|
22.04.2005 | 4th project workshop with participation of all co-operation partners at "Waldhotel Zollernblick" near Freudenstadt |
|
17.03. + 18.03.2005 | Visit of Federal Minister of Education and Research, Edelgard Bulmahn, in the project area with project presentation, building site and cave inspection as well as an audience with Sultan Hamengku Buwono X in Yogyakarta |
|
01.03. + 02.03.2005 | Workshop in Yogyakarta within the scope of the IWRM pilot study |
|
24.02.2005 | Handing over of final pre-design with the analogue plan to WIKA, DPW and UGM with detailed discussion over the approach plan |
|
31.01.2005 | Student excursion to Gua Bribin and to the borehole location in the scope of postgraduate program of UGM |
|
09.12.2004 | Company Herrenknecht AG accomplishes break-through with shaft drilling (ø 2,5 m) in 98,4 m depth |
|
09.12.2004 | Coordination meeting concerning the preliminary draft of IWG/IfMB and for further project planning with BATAN, DPW and WIKA in Jakarta |
|
08.12.2004 | Coordination meeting concerning the preliminary draft of IWG/IfMB and for further project planning with BAtAN, DPW and WIKA in Yogyakarta |
|
06.12.2004 | The acting President Susilo Bambang Yudhoyono visits the building site Bribin |
|
21.10.2004 | Project workshop at the IfG of University of Gießen with participation of all Sub project as well as the project agency, the Research Center Karlsruhe |
|
26.08.2004 | The Landesschau BW broadcasts a film documentation about the joint project |
|
06.08.2004 | Coordination meeting concerning the preliminary draft of IWG/IfMB with BATAN, DPW and WIKA in Jakarta |
|
03.08.2004 | Coordination meeting concerning the preliminary draft of IWG/IfMB with BATAN, DPW, WIKA and DIY in Yogyakarta |
|
02.08.2004 | Inauguration of building site with attendance of Indonesisan Minister Research and Technology Mr. Hatta Radjasa and Sultan Hamengku Buwono X |
|
07/2004 | Beginning of shaft drilling with the vertical drilling machine of the company Herrenknecht AG |
|
25.06. – 26.06.2004 | Karstwassersymposium Blaubeuren with a lecture of IWG/IMG about the joint project |
|
18.06. – 20.06.2004 | Presentation of the joint project with an information booth at the anniversary celebration of the city of Karlsruhe |
|
03.06.2004 | A governmental and parliamentary delegation of Yogyakarta Special Province visits the University of Karlsruhe and the company Herrenknecht AG in Schwanau |
|
17.05.2004 | Break through in 98,50 m depth with the second exploratory drilling into Bribin cave |
|
22.04.2004 | Project workshop at the IWG with cooperation of all Sub projects as well as with representatives of the project agency |
|
21.04.2004 | Completion of the internet presence of the joint project |
|
15.04.2004 | Visit of the Indonesian ambassador Mr. Jamtomo at company Herrenknecht AG in Schwanau |
|
29.03.2004 | Second exploratory drilling in the range of the planned hydro-power plant |
|
15.03. + 16.03.2004 | Project workshop at BATAN in Yogyakarta with participation of Indonesian and German project and co-operation partner |
|
07.02. – 13.02.2004 | A delegation of the BMBF / IB (amongst others Mr. Dr. Diehl) accompanied by Prof. Nestmann travels to Indonesia |
|
03.12. – 05.12.2003 | Sultan Hamengku Buwono X visits the BMBF in Bonn, the University of Karlsruhe (Meeting with Minister for Environment B.-W. Ulrich Müller and Mayor Manfred Groh) and the company Herrenknecht AG in Schwanau |
|
01.12. – 05.12.2003 | Seminar „Water Resources Management in Karst Area“ at Sebelas Maret University, Surakarta |
|
25.11.2003 | Project workshop with participation of all Sub projects as well as with representatives of IB (BMBF) and the project agency, the Research Center Karlsruhe |
|
16.08. – 13.09.2003 | Measurement campaign in Gua Bribin and the project area by GIK |
|
29.07.2003 | Audience with Sultan Hamengku Buwono X in Yogyakarta. Representatives of all Sub projects and the project agency present/introduce the joint project |
|
03.04.2003 | Project workshop with participation of all Sub projects AT THE IWG |
|
25.01.2003 | Break through in 103 m depth with the first exploratory drilling into Bribin cave (Start of drilling: End of November) |
|
06.12.2002 | Grant of joint project by BMBF |
|
03/2002 | Completion of the feasibility study |
|
09/2000 – 03/2002 | 4 field investigations in the project area of Gunung Sewu within the scope of IWG's feasibility study |
|
05/2000 | IWG applies for a feasibility study about the joint project at the BMBF |